← Long Lake Duplex Goal

Draw Schedule & Build Timeline β€” Long Lake Duplex Development

Trade-by-trade sequence with Michigan lien-law gates, deposits, draws, and a live timeline slider. Durations are researched production rates scaled to the actual plans: ~3,526 sf per duplex building (2 Γ— 1,763 sf), 44'Γ—52' footprint, 8 buildings in two 4-building waves.

⏱ Timeline Compression β€” drag it, watch the money move

26 months

Baseline 26 months = sequential two-wave build with normal trade gaps. Compression below ~20 months assumes overlapping waves + committed crews; below 18 is aggressive (weather + inspection risk). Cost basis and loan terms come from the editable fields below.

Interest Carry
β€”
β€”
Holding / Site Overhead
β€”
porta-johns, dumpsters, temp power, builder's risk, taxes
Total Time-Driven Cost
β€”
β€”
Saved vs 26-month baseline
β€”
interest + holding combined

Holding default $4,800/mo = porta-johns ~$400 + dumpster pulls ~$1,600 + temp power ~$450 + builder's risk/GL ~$1,400 + land taxes ~$80 + misc site logistics ~$870. Edit to match real bills.

βš–οΈ Michigan Construction Lien Act gates (Act 497 of 1980)

GateWho filesWhenWhy it matters
Notice of CommencementOwner (THE REIF) β€” recorded with Genesee County Register of DeedsBefore any physical work starts; post a copy on site + give to GCSets up the project legally; failure to provide it on request EXTENDS subs' lien windows against you
Notice of FurnishingEach subcontractor / supplier (to owner's designee + GC)Within 20 days of first furnishing labor/materialsProtects the sub's lien rights β€” expect one from every trade; track them as they arrive
Sworn statements + lien waiversGC at every draw; subs sign waivers as paidEvery draw, before funds releaseYour shield: never release a draw without a sworn statement + conditional waivers, full waivers on prior draw
Claim of Lien windowAny unpaid sub/supplierWithin 90 days of their last furnishingA trade's lien exposure doesn't close until 90 days after they finish β€” schedule final waivers accordingly
Michigan Builders Trust Fund ActGC/contractor (MCL 570.151)AlwaysDraw funds are statutory trust funds for subs β€” criminal penalties for misuse; another reason draws follow verified work

Deposits: Michigan has no statutory cap on contractor deposits β€” the 20–25% figure is custom, not law. TR standard: hold deposits to 10–20% for material-heavy trades only (countertops, garage doors, HVAC equipment), $0 deposit for labor trades, and pay everything else on completed-work draws with waivers. Licensed-builder rule: anyone contracting >$600 of residential work needs a Michigan builder/M&A license β€” verify every sub at michigan.gov/lara.

πŸ“† Trade sequence, durations & draws SCALES WITH SLIDER

Durations researched from standard production rates applied to these plans (3,526 sf/building; 8 buildings in 2 waves of 4 with crews rolling building-to-building). Lender draws assume completed-work funding (typical 5–7 draws per building phase; ~14 project-wide). Deposit column = TR recommended max, not law.

#Stage / TradeStartsDurationDepositPaid / DrawLien-law gate

πŸ’° Draw curve β€” when money leaves

Month 1β€”β€”

Spend curve: light early (site/permits ~12%), heaviest through framing-mechanical-finishes (months 30–80% of schedule), tail for punch/landscape/CO. Drives the "avg drawn balance" the interest math uses.